Florida limits retainage on public projects to 5%

Dive Temporary:

  • Following a 40- vote, Florida lawmakers have handed a bill that will restrict the amount of money of retainage that can be withheld from contractor payments on condition and nearby publicly funded tasks to five%. If Florida Gov. Ron DeSantis signs the laws, the new law will go into impact Oct. one, 2020.
  • Presently, contractors operating on community tasks have 10% retainage withheld from their payments right until 50% of the challenge is comprehensive. Then, the retainage price drops to five%. In addition to restricting how substantially retainage community entities are permitted to withhold, the new law will also have to have basic contractors to restrict retainage on subcontractor payments to five% as perfectly. 
  • The new regulation will not apply to tasks valued at $two hundred,000 or considerably less Florida DOT tasks accepted beneath Florida Statutes Ch. 337 and tasks entered into, pending approval or advertised by a authorities entity on or prior to Oct. one, 2020. F.S. Ch. 337 makes it possible for the FDOT to withhold a optimum of 10% retainage if the contractor fails to start a challenge in a timely fashion or falls powering plan on a challenge with flexible start and completion periods.​

Dive Perception:

Retainage is the portion of the contract price that is withheld right until do the job is substantially comprehensive. The condition of Florida founded the present price of retainage in 2005 inspite of an Place of work of Application Plan Investigation and Governmental Accountability study that uncovered subcontractors have been at threat of “waiting for an unreasonable amount of money of time to receive payment” when jobsite delays unrelated to the subcontractor’s do the job happened. 

For instance, in an extreme scenario, an earthwork subcontractor could comprehensive its do the job early in the challenge plan, but the concrete phase of the do the job is held up for causes unrelated to the steps of the earthwork subcontractor. The earthwork subcontractor may have to wait around right until the challenge is 50% comprehensive to receive five% of retainage withheld on its contract. 

There is absolutely nothing in the present or new law that helps prevent a community entity in Florida from keeping retainage at a decrease price and including a customized retainage release plan in contracts or subcontracts. So there is absolutely nothing in the regulation to reduce early-do the job contractors from negotiating the accelerated payment of retainage. 

The operator ought to pay out retainage and any remaining payments inside thirty times of substantial completion, for tasks up to $10 million, and inside 60 times of substantial completion for those valued at more than $10 million.  

Illinois altered its laws in August of past calendar year to cap retainage at 10% on most private tasks, with a reduction to five% once a contractor completes 50% of its contract scope of do the job. This is identical to the Illinois retainage laws governing community tasks.

New Mexico prohibits retainage on community and private tasks, but, in accordance to the American Subcontractors Association’s “Retainage Guidelines in the 50 States 2018,” some house owners and contractors in that condition have altered their design agreements to incorporate a line item of five% to 10% of the contract amount of money for closeout do the job, in essence, obtaining yet another way to withhold the equivalent of retainage.​